The Latest News
Plant Washington air permit doesn’t meet public health standards
added 12.19.11
The state air quality permit for Plant Washington, a proposed 850 mega-watt coal-fired power plant in Sandersville, GA, does not meet national public health standards that even 50 year old coal-fired power plants already meet, according to a court challenge filed today by public interest groups. Read more in the press release.
Learn more about this case »
Previous Case Activity
Victory for clean air in GA: Court rules GA failed to set safe limits on pollutants from coal plant
added 1.5.11
A Georgia court rejected an air permit for a proposed coal-fired power plant, Plant Washington, after SELC and other organizations challenged it in court. The ruling found that the permit failed to set safe limits on pollution from the plant. More details are in the press release.
Judge rules water permits for coal plant are flawed
added 7.26.10
SELC and our partners in Georgia won a key legal victory when a judge ruled that two water permits necessary for the construction of the proposed 850-megawatt coal-fired power plant in Sandersville are legally flawed.
The administrative law judge found that the Georgia Environmental Protection Division (EPD) failed to follow proper procedure in evaluating the interbasin transfer of water from the Oconee River basin to the Ogeechee River basin. Power4Georgians - a consortium of electric cooperatives proposing the project - plans to take 13.5 million gallons a day from the Oconee, and return only 11 percent; the rest of the water will be consumed at the plant as steam or for other uses.
The judge also invalidated a water pollution permit, finding that EPD erred in allowing the facility to monitor and regulate pollution within the facility rather than at the point of discharge, as required by the Clean Water Act.
Read our press release here.
Coal plant in GA challenged on its negative impacts
added 5.10.10
Public interest groups today filed legal challenges to three state water and air permits for the proposed 850 mega-watt Plant Washington coal power plant in Sandersville, GA. According to documents filed in the Office of State Administrative Hearings, Georgia Environmental Protection Division permits for the proposed Plant Washington would illegally degrade water resources for users and downstream communities along the Oconee River, and allow high levels of harmful pollutants into the air residents breathe. More information is in the press release.
Learn more about this case »